Raw Material and Ore Preparation Facilities Automation
Location :
Karabük / TURKEY
Customer :
KARDEMİR
Starting Date :
01.01.2000
End Date :
01.01.2000
Sectors
Iron & Steel
BUSINESS DETAIL
Total I/O numbers are 3.518.
Our modernization includes PLC & SCADA, Stacker1&2 / Reclaimer1&2 drive and control system of Mineral Processing and Blending plants in KARDEMİR A.Ş.
From project drawing to panel manufacturing, from PLC program to SCADA, testing and simulation of every point was completed before the existing Siemens S5 panels were dismantled.
From project drawing to panel manufacturing, from PLC program to SCADA, testing and simulation of every point was completed before the existing Siemens S5 panels were dismantled.
By means of this:
Blend Plant (812 I/O)
Removing old boards and installing new boards: 8 hours
Testing and commissioning: 2 hours
Total: 10 hours
Ore Preparation Plant (1.640 I/O)
Removing old boards and intalling new boards: 15 hours
Testing and commissioning: 6 hours
Total: 21 hours
The commissioning processes were completed in a very short time, such as the facility, and the facility was given to the use of the enterprise, and the revisions requested by the enterprise were carried out in a way that would not disrupt production.